The termination of public works contracts may result in the early cessation of a project, administrative repossession, enforcement of guarantees, hiring of another contractor, and the demand for substantial compensation. Therefore, a termination decision should not be analyzed solely in light of the delay or the clause invoked by the project owner.
It is necessary to assess the contract, the specifications, the work plan, the successive changes to the execution, the consignment and suspension records, the communications between the parties and, above all, the effective attribution of the breach.
The regime results primarily from Public Contracts Code (CCP), with general rules applicable to administrative contracts and specific provisions for public works contracts. Furthermore, Decree-Law No. 177/2026, of September 4, introduced relevant changes to the CCP which, as a rule, come into force on October 1, 2026.
What is the termination of a public works contract?
Resolution is a way to terminate a contract before it has been fully performed, based on a legally relevant circumstance stipulated by law or the contract itself.
In the context of public works contracts, it may be associated with a serious breach of contract by the contractor, a breach by the client, specific circumstances of the execution of the project, or reasons of public interest.
Article 330 of the CCP (Code of Civil Procedure) includes termination among the causes for the extinction of administrative contracts, along with fulfillment, definitive impossibility, other causes recognized by civil law, and revocation.
What constitutes contract termination?
The termination of a contract ends the contractual relationship based on a situation that legally justifies the cessation of the relationship. It should not, therefore, be confused with a simple decision to stop executing the work or with the informal cancellation of the contract by one of the parties.
When the initiative belongs to the public contracting authority, the unilateral resolution constitutes an administrative act under Article 307 of the Public Contracts Code. This has important consequences regarding the justification, procedural guarantees, and the possibility of judicial challenge.
In public works contracts, the general principles of articles 332 to 335 coexist with the specific principles provided for in articles 405 and 406 of the Public Contracts Code.
What is the difference between resolution, revocation, and expiration?
Termination presupposes a legal or contractual basis that allows the contract to be ended, often related to breach of contract or unforeseen circumstances.
Revocation is different. Under Article 331 of the CCP, the parties may revoke the contract by agreement, specifying the effects thereof in that agreement. Therefore, there is not necessarily a breach of contract by either party.
In general terms, expiry refers to the termination resulting from the occurrence of a fact, term, or condition to which the law or the contract attributes this effect, without necessarily corresponding to a penalty for non-compliance. The CCP itself contains specific situations of expiry for certain categories of contracts.
Who can terminate a public works contract?
Both the client and the contractor may, under certain circumstances, have grounds to terminate the contract. However, their powers are not equivalent, and the applicable procedures may differ.
This distinction is particularly important because the public contracting authority has powers of authority in the execution of administrative contracts that are not recognized, under the same terms, to the private co-contractor.
Resolution initiated by the owner of the work.
The project owner may rely on general grounds for imposing sanctions as set out in Article 333 of the Public Contracts Code and on specific grounds applicable to public works contracts as set out in Article 405.
The situations covered include certain delays attributable to the contractor, unjustified suspensions, deviations from the work plan, serious or repeated breaches of safety rules, and failure to correct certain defects.
The existence of a problem in the execution of the project does not, however, mean that the termination is automatically valid. The grounds invoked must be effectively met, and there must be a relationship between the established facts and the legal regime used.
Resolution initiated by the contractor.
The contractor also has mechanisms to terminate the contract when the breach or certain circumstances are attributable to the public contracting authority.
Article 332 establishes general grounds for termination at the initiative of the co-contractor, while Article 406 contains grounds specifically applicable to public works contracts.
Exercising this right requires special caution. The method of resolution depends on the specific grounds used, with Article 332 establishing, as a rule, that the right is exercised through judicial or arbitral means, and providing a specific regime for certain situations of non-payment.
Resolution for reasons of public interest.
There is also a completely different reality: resolution for reasons of public interest.
Under Article 334 of the Public Contracts Code, the public contracting authority may terminate the contract for reasons of public interest, provided that the decision is duly justified and accompanied by the payment of fair compensation to the other contractor.
In this case, we are not necessarily dealing with a sanction against the contractor. The basis lies in the public interest pursued by the Administration, and this results in a specific compensation regime.
When can the owner of the project terminate the construction contract?
Article 405 of the CCP establishes specific grounds for the termination of construction contracts by the client. These grounds must be considered in conjunction with the general rules for breach of contract and punitive termination.
Definitive breach attributable to the contractor.
Article 333 allows for termination as a sanction when there is a definitive breach of contract due to a fact attributable to the other contracting party.
This formulation contains two essential elements: the breach must be definitive and attributable to the contractor.
A delay caused, wholly or partially, by the unavailability of the site, changes introduced by the client, additional work, suspensions, delays in the approval of solutions, or interference from third parties cannot be automatically treated as a delay exclusively attributable to the contractor.
Delay in the start or execution of work.
Article 405 specifically provides for the possibility of termination when there is a delay in the commencement of the work attributable to the contractor exceeding 1/40 of the work execution period.
During execution, delays can also become significant due to general rules on breach of contract, provisions relating to the work plan, and clauses of the contract itself.
The element of accountability remains central. It is necessary to reconstruct the chronology of the project and determine which events had an actual impact on the contractual deadline.
Unjustified suspension of work by the contractor.
The project owner may have grounds for termination when the contractor suspends work without legal or contractual justification, and this suspension results in serious harm to the public interest, as provided for in Article 405.
The classification of the suspension must be rigorous. A work stoppage motivated by legally justified circumstances should not be treated in the same way as a unilateral and unjustified suspension of work.
Deviations from the work plan
The work plan is an essential element for determining the progress of the project and identifying deviations that could compromise the agreed deadlines.
In the event of certain deviations, the CCP provides mechanisms designed to allow for the recovery of the delay. Article 404 specifically regulates the submission of a modified work plan and the consequences of further deviations.
Resolution may become possible in the situations specifically provided for in Article 405, but the mere observation of a difference between the actual execution and the initial planning is not sufficient, in isolation, to demonstrate all the prerequisites for resolution.
Failure to comply with occupational health and safety rules.
Serious or repeated non-compliance with legislation on occupational safety, hygiene and health constitutes one of the grounds expressly provided for the termination of the contract by the client.
The legal wording itself demonstrates that it is not a matter of occasional irregularity. The seriousness or repetition of the behavior is relevant to fulfilling the grounds for the decision.
Failure to assign the work
The contractor's failure to appear for the handover can also lead to termination, but Article 405 establishes specific conditions.
A single absence is not enough. The law stipulates the need for a new notification and a further absence without justification accepted by the owner of the work, under the specific terms established by the CCP (Public Contracts Code).
Non-compliance related to supplementary work.
The regulations governing supplementary works are particularly sensitive because they can generate disagreements regarding the obligation to perform them, the price, the deadline, and the impact of these works on the project planning.
In the wording of the Public Contracts Code applicable before the entry into force of the 2026 reform, Article 405 provides for resolution in certain situations related to the failure to commence the execution of complementary works after the complaint procedure and reiteration of the order by the owner of the work.
The legality of the order itself, the complaint filed by the contractor, and the deadlines observed must be analyzed before concluding that there are grounds for terminating the contract.
Failure to correct defects in the work.
The contractor's responsibility does not necessarily end with provisional acceptance.
During the warranty period, obligations related to defects in the work remain in effect. Article 405 provides for the possibility of termination if certain defects detected during this period are not corrected, or if the work is not repeated or defective equipment is not replaced in accordance with legally established terms.
What is the sanctioning resolution for a public works project?
A sanctioning resolution constitutes a reaction by the public contracting authority to a sufficiently serious breach of the obligations assumed by the other contracting party.
Article 333 of the CCP provides, among other grounds, for definitive non-compliance attributable to the contractor, non-compliance with legitimate orders related to the execution, repeated opposition to inspection, certain irregularities in the assignment or subcontracting, non-compliance with judicial or arbitral decisions, and failure to renew the guarantee.
This is a particularly serious consequence, and therefore the justification for the decision and the demonstration of its respective assumptions are of particular importance.
When does a definitive breach of contract occur?
Not all delays constitute definitive non-compliance.
Article 325 of the CCP stipulates, in general terms, that in the event of non-compliance attributable to a co-contractor, the public contracting authority must notify them to comply within a reasonable period, unless compliance has become impossible or interest in the service has been lost.
If the breach persists after this period, the possibility of termination due to definitive breach may arise.
The terms of the contract and specifications should also be considered, as they may assign specific consequences for failure to meet certain deadlines, provided that these clauses are legally valid and correctly applied.
O Judgment of the Central Administrative Court of the North of August 5, 2026, case no. 00311/18.9BEPRT, This clearly demonstrates the importance of this concrete analysis. In a dispute involving delay and a sanctioning termination, the Court held that certain subsequent actions by the parties, including new opportunities for performance and the subsequent provisional acceptance without reservation of the performance in question, were relevant to determining whether the definitive breach used to justify the termination still existed. The termination decision was ultimately annulled due to the lack of this legal basis.
This case illustrates an essential principle: it is not enough to historically identify a delay. It is necessary to determine whether, at the time of resolution, the legal basis for terminating the contract actually exists.
Is a formal request necessary before resolution?
Often, yes, but not in all situations.
Article 325 establishes as a rule the notification of the co-contractor to comply within a reasonable period before the situation of non-compliance becomes grounds for termination due to definitive non-compliance.
However, there are exceptions, namely when performance has become impossible or the contracting public entity has lost interest in the service. The framework may also be conditioned by valid contractual clauses that attribute essential character to certain deadlines.
Therefore, the answer depends on the grounds used. A resolution based on definitive breach should not be confused with a resolution based directly on one of the specific situations provided for in Article 405.
Does the resolution have to respect the principle of proportionality?
The sanctioning resolution constitutes the exercise of public power with particularly intense consequences for the co-contractor.
Administrative action is subject to the general principles of administrative activity, including proportionality, good faith, reasonableness, and the pursuit of the public interest.
In assessing a resolution decision, it may therefore be relevant to understand whether the specific gravity of the facts, the accountability, the parties' prior conduct, the possibilities for correction, and the impact on the public interest effectively justified the measure adopted.
Can the contractor also terminate the public works contract?
Yes. The law does not reserve the right of termination to the owner of the work.
In addition to the general principles set out in Article 332, Article 406 establishes situations specific to public works contracts.
Failure or delay in the commencement of work.
The contractor may have the right to terminate the contract if the commencement of work does not occur within six months of the contract's signing due to a reason beyond their control.
The awarding of the contract is particularly important because it determines the effective start of the works and, consequently, the entire project schedule.
Prolonged interruption due to partial consignments.
When partial payments have been made, the delay in subsequent payments may justify termination if it causes an interruption of work exceeding the period established in Article 406.
It is important to document not only the dates of the assignments, but also the relationship between the delay in making the areas available and the actual impossibility or interruption of execution.
Significant reduction in the value of the work.
Article 406 also covers situations where changes to the contracted work, due to reasons not attributable to the contractor, lead to a reduction in the contract price exceeding the legally established limit.
The calculation must be carried out in accordance with the regime applicable to the specific contract and with the version of the Public Contracts Code that is temporally applicable to it.
Prolonged suspension of the project.
Maintaining the suspension for relevant periods may also give the contractor the right to terminate the contract.
Article 406 distinguishes, in particular, between situations of force majeure and suspensions resulting from events attributable to the owner of the work, and establishes specific time limits for each.
Damages that make maintaining the contract excessively burdensome.
The specific regulations for construction contracts also cover certain situations of damages suffered by the contractor, combining Article 406 with Article 354 of the Public Contracts Code.
In parallel, the general regime of Article 332 contemplates the abnormal and unforeseeable alteration of circumstances, subject to specific assumptions and consideration of the impact that the resolution may have on the public interest.
Failure by the public contractor to fulfill its payment obligations.
Article 332 gives particular weight to non-payment. Among the grounds provided is the failure to meet financial obligations for a period exceeding six months or when the debt, excluding interest, exceeds 25% of the contractual price.
In these cases, there is an important peculiarity. The right of termination can be exercised by means of a declaration to the public contracting authority, taking effect 30 days after its receipt, unless the outstanding obligations and the respective default interest are paid in the meantime.
In other situations foreseen in article 332, the resolution is, as a rule, exercised judicially or through arbitration.
How does the process of resolving a public works contract work?
The procedure depends on the nature of the resolution and the grounds used. In a sanctioning resolution initiated by the project owner, a generic communication of dissatisfaction with the execution of the work is not sufficient.
Communication of intent to terminate the contract.
The contractor must have a concrete understanding of the facts being attributed to him and the relevant legal framework, allowing him to understand why the client believes the conditions for termination are met.
Justification for the resolution decision
The decision must identify the relevant facts and establish the link between those facts and the grounds for resolution used.
Generic expressions such as project delay, non-compliance with the plan, or lack of resources may prove insufficient when not accompanied by a concrete demonstration of the periods in question, obligations violated, responsibility for the delay, and their respective consequences.
Preliminary hearing with the contractor
The preliminary hearing takes on particular importance when the resolution is exercised as a sanction.
Article 307 classifies unilateral termination by the public contracting authority as an administrative act, and Article 329 includes termination among the sanctioning measures applicable to contractual breach.
Case law has reinforced the importance of procedural safeguards in the application of sanctions during the execution of construction projects. Judgment of the TCAN of May 9, 2025, case no. 01763/15.4BEPRT, In a case concerning financial penalties in a public works project, the Court considered the prior hearing an essential formality and stressed that the communication must provide the factual and legal elements necessary for an effective adversarial process.
Although this process concerned pecuniary sanctions and not specifically a resolution, the decision is particularly relevant for understanding the procedural requirements associated with the exercise of sanctioning powers in the context of the execution of public contracts.
Final resolution decision
After considering the position presented by the contractor, the competent authority must decide whether or not to maintain its intention to terminate the contract.
The final decision must address the relevant issues raised, particularly when discussing causes of delay attributable to the client, extensions of deadlines, additional work, suspensions, or other events likely to alter the initial assessment.
Notification of the decision
The decision must be formally notified to the contractor. From that moment on, it becomes particularly important to immediately analyze the available means of response and their respective deadlines.
Depending on the case, it may be necessary to consider a action within the scope of administrative litigation and, when the respective conditions are met, measures designed to prevent the immediate effects of the decision from rendering a future judicial decision useless.
Communication to the competent authorities.
The resolution may also trigger reporting obligations to public entities, a matter that was updated in Decree-Law No. 177/2026.
What changes with Decree-Law No. 177/2026?
Legislative update: o Decree-Law No. 177/2026, of September 4, The legislation was published on September 4, 2026, and enters into force on October 1, 2026. Regarding contract execution, the temporal rule is particularly important: the changes generally apply to procedures initiated after the legislation comes into force and to contracts concluded following those procedures. The legislation contains specific exceptions for certain matters.
In the new wording of Article 405, it is now expressly stipulated that, upon termination of the contract, the owner of the work immediately takes administrative possession of the work, with the assistance of the contractor.
The obligation to communicate is also updated. The new wording stipulates that the owner of the work must inform the Institute of Public Markets, Real Estate and Construction, IP, within 10 days after the resolution becomes unchallengeable, for publication in the public area of the public contracts portal.
These changes should not be automatically applied to a project simply because the dispute occurs after October 1, 2026. Before using the new wording of the Public Contracts Code, it is necessary to verify when the procedure that originated the contract was initiated and the rules of application over time foreseen in Decree-Law No. 177/2026 itself.
What are the consequences of terminating the contract?
The effects of the resolution may be substantially more complex than the mere cessation of work. They may involve significant financial liabilities for both parties and condition how the work is subsequently completed.
What happens to the work that has already been completed?
The resolution does not materially eliminate the work already carried out. It is necessary to ascertain what has actually been executed, measured, accepted, paid for, and possibly subject to corrections.
Measurement reports, the contract account, completed work, and existing defects can be decisively important in determining the amounts still owed and the credits of each party.
Can the owner of the property take possession of it?
There are administrative possession mechanisms related to the execution of construction projects. The reform introduced by Decree-Law No. 177/2026 makes this consequence especially clear by adding to Article 405 the express provision that, after the termination, the owner of the work immediately takes administrative possession of the work, with the assistance of the contractor.
Even before the resolution, there may be specific situations in which the CCP allows for administrative takeover or execution of the works directly or through a third party, particularly within the framework of deviations from the work plan.
What happens to the amounts still to be paid?
The amounts owed do not necessarily disappear with the settlement.
An assessment must be made of the work performed, existing credits, any penalties, indemnities, compensations, and other liabilities arising from the contract.
In the sanctioning resolution, article 333 establishes that, if the co-contractor is liable, the respective amount may be deducted from the sums due to them.
Can the security deposit be executed?
There may be grounds for enforcing guarantees provided by the contractor.
Article 333 expressly provides that the deduction of liabilities from the amounts due does not prejudice the possibility of the contracting authority enforcing the guarantees provided by the co-contractor.
However, the existence of a resolution does not mean that any amount of the security deposit can be automatically appropriated. It is necessary to analyze the object of the guarantee, the damages claimed, and the specific conditions for its execution.
Can another contractor be hired to complete the work?
Yes, the completion of the project may be entrusted to another economic operator.
This contract is, however, subject to the applicable public procurement rules. The termination of the first contract does not, in itself, constitute a general exemption from compliance with the Public Procurement Code in the selection of a new contractor.
Could there be liability for the costs of the new procedure?
Yes. Article 333 expressly provides that liability arising from the sanctioning resolution may cover damages associated with the need to carry out a new contract formation procedure.
The existence and extent of this liability must, however, be demonstrated. There must be a legally relevant link between the breach attributable to the contractor and the damages actually claimed by the client.
Is there a right to compensation for the termination of the construction contract?
The answer essentially depends on the grounds that led to the termination and the party responsible for ending the contract.
Compensation when the termination is attributable to the contractor.
When a sanctioning resolution is valid and results from a breach attributable to the contractor, the client may claim damages caused by the breach under the applicable legal terms.
Among other things, the costs directly associated with the default and expenses resulting from the need to resort to a new procedure to complete the outstanding payments may be at stake.
Compensation when the breach is attributable to the owner of the work.
When the public contracting authority definitively breaches the contract, the contractor may, in addition to any right of termination under Article 332, be entitled to compensation for damages resulting from the breach.
The analysis of damages typically requires accounting, contractual, and technical documentation that allows for establishing the damage and its link to the owner's conduct.
Compensation for termination due to reasons of public interest.
In this case, there is a particularly clear set of rules.
Article 334 establishes that termination for reasons of public interest must be accompanied by fair compensation to the other contractor.
The law stipulates that this compensation includes both actual damages and lost profits, and also applies specific rules to the calculation of any anticipated gains.
Emerging damages and lost profits
Emergent damages generally correspond to the losses actually suffered in the injured party's assets.
Lost profits correspond to the benefits that would foreseeably have been obtained if the event giving rise to the right to compensation had not occurred.
Its quantification should not be based solely on abstract projections. Contract details, project margins, costs already incurred, cost structure, work that was not performed, and expenses avoided may all be relevant to the calculation.
How to contest the termination of a public works contract?
A decision to terminate the contract must be analyzed simultaneously from a legal, contractual, documentary, and technical perspective. Focusing the defense solely on the article cited by the owner of the work may leave out some of the most important arguments.
Analyze the grounds invoked for the resolution.
The first step is to identify exactly what grounds are being used: definitive breach of contract, delay, unjustified suspension, deviation from the work plan, violation of a clause in the specifications, or other grounds.
Next, it must be verified whether the specific facts indicated correspond to the assumptions required by the rule.
Verify whether the breach is attributable to the contractor.
This analysis is often crucial.
A project may be behind schedule without the contractor being entirely responsible for the delay. Late availability of work fronts, alterations, instructions from the client, supplementary work, suspensions, delays in approving solutions, and interference from third parties can all affect the schedule.
It is necessary to reconstruct the execution of the work and demonstrate the causal relationship between each event and the contractual deadlines.
To verify compliance with the right to a prior hearing.
It is not enough to verify whether a communication called a prior hearing took place.
It is necessary to ascertain whether the contractor was provided with the facts, grounds, and elements necessary to exercise an effective right to reply, and whether the arguments presented were actually considered before the final decision.
Assess the proportionality of the decision.
The seriousness of the breach, the behavior of the parties throughout the project, any previous opportunities for correction, the continued validity of the grounds at the time of the decision, and the appropriateness of the resolution in light of the public interest at stake must also be analyzed.
Gather documents, notifications, work plan, and correspondence related to the project.
In disputes related to construction contracts, documentation tends to be as important as the legal framework.
Emails, meeting minutes, official documents, inspection reports, execution orders, extension requests, and successive versions of the work plan can significantly alter the assessment of an alleged non-compliance situation.
Legal challenge to the resolution decision
Since unilateral termination by the public contracting authority is an administrative act, there may be grounds for challenging it before administrative courts.
The procedural strategy and deadlines depend on the specific configuration of the act and the claims to be made. When the immediate effects of the resolution may cause significant damage or make restoring the previous situation particularly difficult, the potential use of precautionary measures provided for in administrative litigation should also be considered.
Support from a team with experience in Public procurement It allows for cross-referencing the legal framework with the procedural documents and all the documentation produced during the execution of the project.
Arbitration in public contracts
Certain disputes relating to public contracts may be submitted to arbitration, depending on the contract, the arbitration agreement and the applicable legal regime.
This avenue is also relevant because Article 332 provides, for various grounds for termination initiated by the contracting party, the exercise of the right through judicial means or by resorting to arbitration.
Decree-Law No. 177/2026 also introduces changes in the area of alternative dispute resolution. This is one of the matters for which the decree establishes specific temporal rules, so, from October 1, 2026, the new wording must be verified even for certain procedures or contracts already underway.
You can also check the area of Arbitrage to understand the framework of this form of dispute resolution.
What documents should be analyzed when considering a resolution?
When a notice of intent to terminate the contract is issued, it is advisable to quickly gather all the documentation that allows for the legal and technical reconstruction of the work's execution. Among the most relevant elements are usually:
- Construction contract and its annexes;
- specifications and procedural documents;
- initial work plan and all versions subsequently approved or submitted;
- consignment records and partial consignments;
- Suspension, restart, measurement, acceptance and non-acceptance records;
- orders, notifications and instructions issued by the owner of the work and by the inspection authorities;
- Requests for clarification and their respective responses;
- complaints, reservations and communications submitted by the contractor;
- Requests for deadline extensions and respective decisions;
- documentation relating to supplementary work, work that is not required and changes;
- Records of delays, their causes, and their impact on the project's critical path;
- invoices, measurement reports, payments and amounts still owed;
- documents relating to the security deposit and other guarantees provided;
- Minutes from construction site meetings, inspection reports, emails, and other relevant correspondence.
The analysis must be chronological. In many processes, a single document may seem to demonstrate non-compliance, but the complete sequence of communications reveals extensions, changes, or subsequent behaviors inconsistent with the interpretation initially presented.
What to do when faced with an intention to terminate a public works contract?
Receiving a proposed resolution requires a swift, but not hasty, response. A preliminary hearing can be a crucial opportunity to prevent a proposed decision from becoming a final act with significant economic and operational consequences.
The primary objective should be to preserve the evidence. Documents, reports, versions of the work plan, and communications related to the project should be organized before preparing the response.
Next, it is necessary to reconstruct the facts chronologically, identify the legal basis invoked by the owner of the work, and test each of its assumptions.
Particular attention should be paid to attribution. When there are contributing causes of delay, changes to the work, additional work, suspensions or events attributable to the client, these elements must be related to the planning and the dates actually affected.
It is also important to avoid statements, acceptances, or operational decisions that could subsequently harm the company's legal standing. The legal strategy should, whenever possible, be coordinated with the technical management of the project.
Anyone facing an intention or decision to resolve a resolution can seek support in the area of public works and contracts.
How can a law firm help in resolving public works contracts?
A dispute over the resolution of a public works contract is rarely simply a matter of interpreting an article of the Public Contracts Code. The decision depends on the interaction between administrative law, public procurement, contractual clauses, technical documentation, and events that occur during months or years of execution.
A law firm specializing in this area can intervene even before the final decision, namely by analyzing the intention to resolve the dispute and preparing for the preliminary hearing.
Legal support may cover, among other matters:
- analysis of the contract, terms of reference and applicable legal regime;
- evaluation of the principles used for the resolution;
- A chronological reconstruction of the relevant events of the undertaking;
- analysis of the attribution of delays, suspensions and deviations from the work plan;
- Preparing responses to notifications and preliminary hearings;
- Analysis of contractual penalties, indemnities, guarantees and compensations;
- support in negotiations aimed at preventing or framing the termination of the contract;
- Challenging administrative acts related to the resolution;
- Monitoring of precautionary measures, administrative actions and arbitration;
- Quantification and claim for damages resulting from breach of contract or termination.
A CSG Solicitors provides advice in Public and Administrative Law and public procurement, including matters related to the execution and termination of public works contracts.
Once a notice of termination or a final decision has been received, the analysis should be carried out with particular attention to the applicable deadlines. It may Contact CSG Advogados to request a legal assessment of the documentation and the grounds for the resolution.
Conclusion
The termination of public works contracts is one of the most serious consequences that can occur during the execution of a public contract. It can result from breach of contract by the contractor, breach of contract by the client, specific grounds of the contracts, or reasons of public interest, but each of these situations is subject to different assumptions.
A delay, a deviation from the work plan, or other breach of contract does not, in itself and under any circumstances, justify the termination of the contract. It is necessary to determine the seriousness of the facts, their attributable to the parties, the contractual framework, the procedures adopted, and the actual existence of grounds for termination at the time the decision is made.
Recent case law confirms precisely the importance of this individualized analysis. Contract, specifications, work plans, records, communications, extensions, additional work, and subsequent conduct of the parties can be decisive in determining whether the termination is legally valid or whether there are grounds to contest it.
Bibliographic references
- Public Contracts Code, approved by Decree-Law No. 18/2008, of January 29, consolidated version..
- Decree-Law No. 177/2026, of September 4, amending and republishing the Public Contracts Code..
- Central Administrative Court of the North, Judgment of August 5, 2026, case no. 00311/18.9BEPRT.
- Central Administrative Court of the North, Judgment of May 9, 2025, case no. 01763/15.4BEPRT.
Note: The information presented in this article is for informational purposes only and should not be interpreted as legal advice. While we have made every effort to ensure the accuracy of the content, we accept no responsibility for any inaccuracies, omissions, or legal changes that may occur after publication. If you are facing a specific situation or have questions about any matter covered, we strongly recommend consulting a solicitor or legal expert for advice tailored to your circumstances.
Latest Articles
CSG Lawyers – Catarina S. Gomes Lawyer
In the office Lawyers in Braga – Catarina S. Gomes, you will find a team of experienced and highly qualified professionals.
The firm offers a wide range of legal services, including client advisement, contract negotiation, divorce, probate, litigation, court representation, and more.
Catarina S. Gomes and her team of Lawyers in Portugal are always ready to respond to their clients' needs, constantly seeking the best solutions for each case, regardless of the complexity.
All lawyers on the team are committed to the highest ethical and professional standards in all their activities, thereby ensuring that clients' interests are always protected and defended fairly and impartially.
If you are looking for a trustworthy and experienced law firm in Braga, Portugal, the team led by Catarina S. Gomes will be ready to assist with all your legal needs, offering a personalised and effective service.
Exercise your right now with qualified help.